Construction of Bridge across Creek in T.P. No.43 joining Bamroli and Bhimrad near Ashirwad Enclave, Surat.

01 Location : Near Ashirwad Enclave, Althan - Bhimrad, Surat.
02 River/ Nala/ Creek : Creek
03 Lane : Six Lane
04 Year of Construction : April-2014
05 Awarded Cost : Rs. 18,90,32,466=49
06 Details of Bridge :  
  (i) Length of Bridge      
   (Between ends of Decking)
: 225.00mt.
  (ii) Number of Span : 09 (Nine)                                  
  (iii) Span Length : 25.00mt.
  (iv) Carriage Way : 10.50mt + 10.50mt = 21.00mt.
(Three lane Up + Three lane Down)
  (v) Length of R.C.C.
     Approaches &Returns
: (1) Bamroli side - 3.90mt + 171.42m=175.32mt.
(2) Bhimrad side - 3.90mt + 71.17m= 75.07m
07 (i)   Design Discharge : N. A.
  (ii)  Design H.F.L. : 7.40mt.
  (iii) Type of Bridge : High Level Creek Bridge
  (iv) Finished Road Top Level : 10.606mt.
08 Structural Details    
  (i) Foundation : Pile Foundation 1000 mm dia
  (ii) Substructure : Rectangular Pier & Abutment wall
  (iii) Superstructure : PSC I Girder, Deck Slab
  (iv) General Items : (1) Strip seal Expansion joint
(2) Elastomeric Bearing
09 Name of Contractor : Rachna construction co., panoli
10 Name of Design Consultant : (Pankaj Patel & Associates, Ahmadabad )
Pankaj M Patel Consultant Pvt Ltd., Ahmadabad
11 PMC : Mahimtura Consultants Pvt Ltd, Mumbai