Road Development

Below are the Road Development Project Details:

Sr. No. Name of Work Tender Amount/Estimated Amount (In LACS) Expenditure Till 31/03/2021 (In LACS) Total Expenditure in Tender (In LACS) Work Order Date Probable Date of Completion of Project
1 Polymeric/ACC marg technology. (Phase-10)  2008.51 1781.42 1781.42 01/10/2020 31/12/2021
2 Package-13 C.C. road from Hazira road (Pal-R.T.O. junction) to Palanpur gam canal culvert.  2130.09 1827.80 1827.80 10/01/2018 Work Completed
3 Package-15  C.C. road on both side of existing canal from palanpur canal culvert to Bhesan junction. 3786.00 2892.68 2892.68 24/10/2017 Work Completed
4 Package 15 (A)  C.C. road on both side of existing canal from Bhesan Junction road to SUDA Limit in WZ. 1344.00 1408.10 1408.10 25/02/2019 Work Completed
5 Package-18 Rigid & flexible pavement on either side of canal, storm water drg. network & allied work from BRTS- Panas -Bread linear circle- Soham circle. 2041.15 1508.89 1508.89 15/10/2018 30/06/2021
6 MICROSURFACING PACKAGE-6 360.09 281.56 281.56 06/11/2018 Work Completed
7 C.C. road from Dindoli flyover to Udhna main road. 999.15 0.00 0.00 25/02/2019 Work Completed
8 Construction of capet/recarpet layers by using shredded plastic waste per new design 239.00 0.00 0.00 11/11/2020 30/11/2021
9 MICROSURFACING Package-7 504.21 483.49 483.49 05/03/2019 Work Completed
10 MILLING work PHASE -11 103.42 17.20 17.20 22/01/2021 22/10/2021
12 C.C.ROAD: East Zone MOTAVARACHHA VIP circle to RAM Chowk. 2081.19 2387.30 2387.30 18/06/2019 31/12/2021
13 C.C.ROAD: East Zone RAM chowk to Abrama Check post 2079.78
14 CC Road Linking Road To Varachha main road & Vallbhcharya Road, East Zone 127.98 0.00 0.00 12/12/2020 11/12/2021