On going Projects
| Sr No | Project Area | Main Project | Sub Projects | Details of Project | Unit | Project Cost (Rs '000) | Timelines / Completion Date (targated) as per SMC's Budget (2011-12) |
Current Status of the Project |
Remarks |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Umra South | Equipments | SETC of Mechanical Equipments for Umra South SPS | 19 | MLD | 15000 | 12 months | Tendering stage | -- |
| 2 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | Drainage Pipeline Magob main | 10.25 | Km | 44231 | 12 months | Work In Progress | Project Under Jnnurm |
| 3 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | Drainage Pipeline Magob Branch | 22.25 | Km | 39563 | 12 months | Work In Progress | Project Under Jnnurm |
| 4 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | Drainage Pipeline Puna | 34.5 | Km | 82270 | 12 months | Work In Progress | Project Under Jnnurm |
| 5 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | Drainage Pipeline Sarthana | 19 | Km | 44904 | 12 months | Work In Progress | Project Under Jnnurm |
| 6 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | Rising Main between SPS to STP New East Area | 11 | Km | 205260 | 12 months | Work In progress | Project Under Jnnurm |
| 7 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | Sarthana SPS | 9 | MLD | 9931 | 12 months | Work In Progress | Project Under Jnnurm |
| 8 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | Puna SPS | 32 | MLD | 25326 | 12 months | Work In Progress | Project Under Jnnurm |
| 9 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | Magbo SPS | 53 | MLD | 52334 | 12 months | Work In Progress | Project Under Jnnurm |
| 10 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | SETC of Electrical Equipments for Sarthana SPS | 9 | MLD | 12500 | 6 months | Work In progress | Project Under Jnnurm |
| 11 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | SETC of Electrical Equipments for Puna SPS | 30 | MLD | 7417 | 6 months | Work In Progress | Project Under Jnnurm |
| 12 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | SETC of Electrical Equipments for Magbo SPS | 53 | MLD | 40000 | 6 months | Work In Progress | Project Under Jnnurm |
| 13 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | SETC of Mechanical Equipments for Sarthana SPS | 9 | MLD | 20135 | 6 months | Work In Progress | Project Under Jnnurm |
| 14 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | SETC of Mechanical Equipments for Puna SPS | 32 | MLD | 25000 | 6 months | Tendering stage | Project Under Jnnurm |
| 15 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | SETC of Mechanical Equipments for Magbo SPS | 53 | MLD | 12776 | 6 months | Work In Progress | Project Under Jnnurm |
| 16 | New Eastern Drainage Zone | Drainage System for New East Area (Puna, Simada) | Sewage Treatment Plant | 66 | MLD | 375963 | 12 months | On verge of commissioning | Project Under Jnnurm |
| 17 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Drainage line for mota Varachha in New Northzone | 22.8 | Km | 33485 | 12 months | Work In Progress | Project Under Jnnurm |
| 18 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Drainage Pipeline for Mota Varachha GEB | 33 | Km | 69374 | 12 months | Work In Progress | Project Under Jnnurm |
| 19 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Drainage line in Uran in New Northzone | 11.5 | Km | 27619 | 12 months | Work In Progress | Project Under Jnnurm |
| 20 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Drainage line in Kosad in New North zone | 32.3 | Km | 94875 | 12 months | Work In Progress | Project Under Jnnurm |
| 21 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Drainage line in Kosad Railway in New North zone | 39.25 | Km | 90660 | 12 months | Work In Progress | Project Under Jnnurm |
| 22 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Drainage line in Vairav in New Northzone | 16.6 | Km | 43861 | 12 months | Work In Progress | Project Under Jnnurm |
| 23 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Drainage line in Vairav STP in New Northzone | 24.9 | Km | 79604 | 12 months | Work In Progress | Project Under Jnnurm |
| 24 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Rising Main line in Vairav in New Northzone | 1.17 | Km | 16048 | 12 months | Work In Progress | Project Under Jnnurm |
| 25 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Rising Main line in Vairav STP in New Northzone | 0.45 | Km | 4820 | 12 months | Work In Progress | Project Under Jnnurm |
| 26 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Treated Seweage Disposal Line for Vairav STP | 10.5 | Km | 202463 | 12 months | Work In Progress | Project Under Jnnurm |
| 27 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Construction of SPS at Vairav | 37 | MLD | 17672 | 12 months | Work In Progress | Project Under Jnnurm |
| 28 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Construction of SPS at Vairav STP | 49 | MLD | 24917 | 12 months | Work In Progress | Project Under Jnnurm |
| 29 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Mechinical Works at Vairav | 37 | MLD | 12869 | 6 months | Tendering stage | Project Under Jnnurm |
| 30 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Mechinical Works at Vairav STP | 49 | MLD | 15969 | 6 months | Tendering stage | Project Under Jnnurm |
| 31 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Electrical Works at Vairav | 37 | MLD | 4132 | 6 months | Tendering stage | Project Under Jnnurm |
| 32 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Electrical Works at Vairav STP | 49 | MLD | 6072 | 6 months | Tendering stage | Project Under Jnnurm |
| 33 | New Northern Drainage Zone | Sewerage System in new Northern Zone area of Surat Municipal Corporation | Infrastructure work i.e roads, compound wall, @ various STP, SPS | NA | NA | 163812 | 12 months | Work in Progress | Project Under Jnnurm |
| 34 | Surat City | SCADA System | 23 SPS and 6 STP's to be covered under SCADA system to save energy and improve efficiency | 34 | Nos | 300000 | 12 months | Work In Progress | Project Under Jnnurm |
| 35 | New South West Drainage area | Providing drainage facilities in New south west area (dummas, Sultanabad, Magdall etc) | Providing drainage facilities in New south west area | 25 | Sq.km | 1370000 | 24 months | Tendering Stage | Project Under NRCP |
| 36 | New South Drainage area | Providing drainage facilities in New south area (Uun, Bamroli, Gabheni, etc) | Providing drainage facilities in New south area | 15 | Sq.km | 3762000 | 24 months | Work In Progress | Project Under SJMMJVY |
| 37 | New South Drainage East area | Providing drainage facilities in New south East area (Parvat, Goladara, Dindoli, etc) | Providing drainage facilities in New south East area | 9.18 | Sq.km | 2786000 | 24 months | Work In Progress | Project Under SJMMJVY |